TTW
TTW

Rail Network Set for Comprehensive Upgrades During Christmas and New Year Period

Sunday, November 17, 2024

Rail network d

With the festive season approaching, passengers are advised to prepare for widespread railway upgrades planned over the Christmas and New Year period, as extensive engineering efforts are set to disrupt some travel routes. Over this time, crews will be engaged in a host of critical projects including the replacement or refurbishment of 45 sets of railway points, four bridge reconstructions, the laying of 40 kilometers of new signaling cables, updates to 17 level crossings, and the activation of seven new signaling systems. These improvements are designed to enhance train punctuality, performance, and overall reliability.

During the festive week—a time when passenger numbers at Network Rail’s stations typically fall by 50-60% compared to early winter months—this engineering work is strategically planned to minimize impact. This period sees around 400 initiatives roll out, notably including:

Significant closures at London Liverpool Street for refurbishments and passenger enhancements, with the station shuttered from Christmas Day to January 2. Greater Anglia and Stansted Express routes will be rerouted through Stratford, and London Overground will halt at London Fields. Alternative travel options include the Victoria line from Walthamstow Central and Seven Sisters, or local buses.

Helen Hamlin, Network Rail’s director of system operations, said:

“Whilst roads are busier during the holidays, it’s actually one of the quietest times on the railway, meaning we can improve things whilst causing less disruption to passengers and freight flows. The major projects we’re undertaking would otherwise take many weekends to complete and cause more disruption to passengers.

“Most of the railway will be open as normal over Christmas and New Year, so passengers can continue to book their travel, just be sure to plan ahead as there will be significant changes to journeys on some routes.”

On the Midland Main Line, works to accommodate East Midlands Railways’ new fleet will disrupt services from December 21 to 29. No trains will operate between London St Pancras and Bedford, and Thameslink will bypass the stretch from St Pancras to Harpenden. Travellers northbound from St Pancras should plan to use alternative London terminals and connecting bus services.

At London Paddington, preparatory installations for new signaling and track equipment essential for HS2 connections at the forthcoming Old Oak Common station will halt all services calling at the station from December 27 to 29. Diversions will redirect most trains to and from London Euston, with key stops at Reading and Ealing Broadway, where passengers can transfer to London-bound Tube services.

In Crewe, extensive resignalling efforts from Christmas Day through January 2 will lead to varied service changes, including a full suspension on December 27 and altered services to Liverpool and Manchester until January 3.

Lastly, track renewals and the construction of the new Cambridge South station—aimed at reducing congestion and improving access to the city’s biomedical campus—will see train services suspended between Royston/Audley End and Cambridge/Cambridge North from Christmas Day to January 5, with bus replacements operating, excluding Christmas and Boxing Day.

Share On:

Subscribe to our Newsletters

Related Posts

Select Your Language

PARTNERS

at-TTW

Subscribe to our Newsletters

I want to receive travel news and trade event update from Travel And Tour World. I have read Travel And Tour World'sPrivacy Notice.